KHD to upgrade the raw material grinding unit of thomas zement in Erwitte, Germany

thomas zement recently awarded Humboldt Wedag GmbH (KHD) a brown field EPC contract for upgrading its raw material grinding plant in Erwitte, Germany. This fast track project comprises

  • Process-, mechanical-, electrical- and civil engineering services
  • Mechanical and electrical equipment supply with the following main machinery equipment:
    • Roller Press for raw material grinding
    • Static V-Separator
    • SKS-High Efficient Dynamic Separator
    • KHD Process Fan type HKF
    • Structural steel supply
  • Erection and installation services for mechanical and electrical equipment as well as structural steel
  • Supervision services for erection, installation and commissioning

Additional to the abovementioned scope of supply, KHD is also responsible for the tie-in of the new equipment to the existing raw material- and product transport, as well as gas handling and treating.

The erection and installation of the new grinding plant will be carried out during operation of the production line followed by a minimal possible switch-over period.

The Erwitte plant in the eastern part of Nordrhein-Westfalen in Germany is rich in tradition and history. Taken over early 2018 the Erwitte plant represents the second cement production line of the thomas group. With this modernization project thomas zement will set up one of the most efficient and environmentally friendly raw material grinding plants in Europe and will strengthen the group´s market position in the competitive cement producer´s environment.

Related topics

Proposal on Dividend Payment

Today the Management Board and the Supervisory Board decided to propose a dividend payment of € 0.12 per non-par-value share entitled to a dividend, at the Annual General Meeting. The total dividend payout amounts to € 5,936,932.44.

Changes to KHD’s Supervisory Board – Proposed Reduction of Number of Members of the Supervisory Board

The Management Board and the Supervisory Board will propose an amendment to the articles of association (reduction of the number of members of the Supervisory Board from six to three persons and reduction of the remuneration for the members) at the Annual General Meeting, which is intended to be held on July 27, 2012.

EUROCEMENT group awards KHD contract for new cement plant in Stavropol / Russia

Leading Russian cement producer EUROCEMENT placed an order for more than € 80 million with KHD for a new cement plant to be built in Stavropol, Russia. The Moscow-based EUROCEMENT group is among the top ten cement producing companies in the world.