Five successful PG tests conducted in the first quarter of 2022

Humboldt Wedag India Pvt. Ltd., a subsidiary of KHD Humboldt Wedag International AG, successfully completed five PG tests in three different projects during the first quarter of 2022.

Chettinad Cement – Dachepalli
The Dachepalli project consisted of two “firsts” for KHD in India. The successful PG test for raw grinding was the first project in India with a Pyrostep® cooler with an intermediate roller crusher installed. The pyroprocess PG test included the first installation of a Pyroredox® reactor that helps to sustainably reduce NOX emissions.

Dalmia DSP Ltd – Kalyanpur
The Kalyanpur project successfully upgraded the pyroprocess and the raw grinding circuit. The pyroprocess was increased from 1900 to 2400 tpd and the raw grinding circuit was successfully increased from 140 to 200 tph.

UTCL Slag Grinding – Patliputra
In 2019, the Aditya Birla Group awarded KHD with a ground granulated blast furnace slag (GGBFS) grinding system with a capacity of 92 tph. The erection work was finished in the year 2021, and the PG test was successfully conducted after six months of commissioning in early 2022.

Related topics

OYAK decides once again for KHD’s COMFLEX® roller press technology for clinker grinding at Aslan Cimento in Turkey

OYAK Aslan Cimento Sanayii T.A.S., awarded KHD Humboldt Wedag a contract for engineering and delivery of equipment to upgrade its cement grinding line. OYAK’s 7th KHD roller press will be installed at its plant in Darica-Kocaeli, Turkey.

Batı Anadolu Group chooses KHD pyro-process technology for new 5,000 t/d kiln line at Batısöke Cement plant in Turkey

The BATI ANADOLU GROUP, Batısöke Cimento Sanayii T.A.S., awarded KHD Humboldt Wedag a contract for engineering, delivery of equipment, training, and erection and com-missioning advisory services for its new 5,000 tpd clinker production line.

Change in Financial Calendar – KHD will publish interim report ahead of schedule

KHD Humboldt Wedag International AG, one of the world’s leading providers of equipment and services for the cement industry, has increased its revenue in the first half of 2013 compared to the same period in the previous year. The Group attained revenues of € 111.5 million – an 8.8% increase over the previous year. Earnings before interest and tax (EBIT) reached € 3.1 million, an improvement of € 0.9 million compared to H1 2012. EBIT margin also increased to 2.8%.

2 Modernization Projects Currently Underway for KHD and HeidelbergCement in Germany

KHD’s 2 modernization projects for HeidelbergCement’s plant in Lengfurt, Germany are currently underway. These projects include the modernization of Raw Meal Grinding Unit with KHD SKS VC 3000 dynamic separator, and the modernization of an existing preheater with KHD’s new PH5835 cyclones. KHD’s responsibility includes manufacturing, erection and commissioning for both projects.

More Good News from KHD in Turkey

KHD’s activity in the Turkish market is continuing to produce positive results, with an order for a new 3,500 t/d clinker production line at the Bolu Cimento’s Kazan plant and successfully completed recent performance test for KCS Kahramanmaras Cimento’s Maras Kiln Line II.